An inspection and test plan (ITP) is the agreement between contractor and client on how quality will be proven. A good one makes inspections predictable; a weak one leads to disputes at handover.
Each activity should be listed in the order it happens, with the acceptance criteria, the reference standard and the record that will be produced.
Hold points, where work stops until the client inspects, should be reserved for steps that cannot be checked later, such as reinforcement before a pour or piping before insulation. Too many hold points slow the site without improving quality.
Finally, the ITP should name who signs each record. When everyone knows their role, inspections happen on time and the turnover package builds itself as the work progresses.